At
9:18am on Sep.16, 2006, Shihua Jiasheng 80,000t/a
Ethylbenzene Plant of Hainan Refinery Continued Project
realized mechanical completion with high standard.
Hainan
Refinery Shihua Jiasheng 80,000t/a Ethylbenzene Plant
include ethylbenzene plant and the auxiliary
ethylbenzene intermediate tank farm, substation and
power distribution cabinet as well as the auxiliary
facility. Since the commencement of the work from
Oct.25,2006, The Tenth Construction Company of SINOPEC
has made fully cooperation with the other parties,
overcame the dificulty in large amount of work, short of
construciton period, deeply crossover in design,
procurement and construction. We have erected 134 sets
of equipment, process piping 16012m, cable 55km,
automatic control cable 178.7km, lighting fixture 500
sets, automatic control equipment 2671 sets. The Tenth
Construction Company of SINOPEC is in the spirit of
taking high responsibility for the owner during the
construction of the project. The company made the most
of its manpower, equipment, management and the advantage
of the resorce, kept promise and careful construction.
In the key management links of purchasing materials,
manufacturing and erection of boiler, strictly operate
according to the procedure, meanwhile strengthen quality
control of welding, once acceptable rate of welding is
up to 98.1%.