9:30 a.m. on May 15, 2007, in the sound of festive
firecrackers, along with a piece of 24t in weight and
20m in length of box type column leaving the ground,
lifting up slowly, the first lifting hook of the frame
box type column for two reactors were started formally.
It indicated that the erection work of Qingdao Refinery
2,900,000t/a heavy oil catalytic cracking plant was
fully spread.
This
plant is the core plant of Qingdao Refinery with maximum
quantity of construction and erection. Meanwhile, it is
very difficult in construction. 50,000m process piping
needs to be erected and the average in./dia is 8.1 inch,
more than 5000t steel structure and 292 sets of
equipment need to be erected.