On
Apr.5, 2008, Xinjiang Weimei Acetylene Project
constructed by the Tenth Construction Company
succeeded in commissioning at one time, got through the
whole process flow smoothly and produced acceptable
acetylene.
It
is known that this project was started to construct
formally on Mar.28, 2008. Air separation unit succeeded
in commissioning at one time on Jan. 5th this year.
Natural gas was fed into acetylene plant on Mar.28 and
oxygen was fed in successfully on Mar.31 and cracking
gas was produced.
(Information provided by News Center)
|