At
10:58 p.m. on Apr.28, 2008, Shenhua Hydrogen from Coal
Plant (105 unit) constructed by the Tenth Construction
Company was realized commissioning successfully at one
time. At 12 o’clock on May 5, through 7 days
continuously operation, the plant produced acceptable
hydrogen. I t indicates that the critical plant of
direct coal liquefaction project was fully completed.
It
is known that this plant shall supply makeup hydrogen
for process of coal liquefaction and hydrogenation
stabilizing unit and hydrogenation revamping unit. It
will take an important role in the whole direct coal
liquefaction plant.
(Information provided by News Center)
|